google-site-verification: google01f337bb9e4b9081.html PMP® Exam Question what first after implemented change with Aileen

PMP® Exam Sample Question on What First after implemented changes with Aileen

implemented changes Dec 22, 2019

The Situation

A PMP Exam Sample Question that looks at what we should do First after an approved change request has been implemented.

Lets look at the PMP Exam Sample Question video.    Make sure you pause the video after you (or I ) read the question.  Answer the question on your own and then listen to my response on why the best answer is best and the other answers are not as good. 

 

Project Management Reality

Have you ever had a requested change approved, and then:

  • never implemented
  • implemented incorrectly
  • implemented correctly but not achieved the outcome expected

Because of this we need a process were we verify that the approved change request has been implemented as approved.

Thought process to get this question right on the PMP® Exam

To get this question right on the PMP® Exam or the CAPM® Exam we really need to understand change control.

We are looking for a process where we verify that the approved change request has been implemented as approved.

I would eliminate Answer A.  Validate scope is a process in which the customer, or their representative, inspects the deliverables to decide if they are going to accept them.  Not the best answer for this question.    

I would eliminate Answer BPerform integrated change control is a process in which change requests are either approved or rejected.   This process does not address implemented changes.  Not the best answer for this question.

I would eliminate Answer CManage quality is a process in which we ensure the organization's quality policy is being followed.  Manage quality has a huge focus on processes and process improvement.  Not the best answer for this question.

Answer D is the best answer.  In the process control quality we want to inspect the deliverables to verify they have been built correctly. We also want to review all approved change requests to verify they have been implemented correctly.   

 A reference you may want to read is:  A Guide to the Project Management Body of Knowledge (PMBOK® Guide) Sixth Edition Section 8.3.2.6 (page 305 in the English Version). 

For invites to free online PMP® Exam Prep Training with Aileen please sign up for our email list at: https://www.aileenellis.com/aileen-s-opt-in-page

 

 