This quiz only pertains to the formula for PERT Estimates above! Goodluck!
Click the button below to start.
Question 1 of 3
Lets assume we have an Activity A and we know that its Most Likely Estimate is that the project will take 22 days, its Optimistic Estimate is 18 days, and its Pessimistic Estimate is 32 days. What is our PERT Estimate?
22 Days
23 Days
24 Days
25 Days
Question 2 of 3
Lets assume we have an Activity B and we know that its Most Likely Estimate is that the project will take 12 days, its Optimistic Estimate is 10 days, and its Pessimistic Estimate is 26 days. What is our PERT Estimate?
10 Days
12 Days
14 Days
16 Days
Question 3 of 3
Lets assume we have an Activity C and we know that its Most Likely Estimate is that the project will take 14 days, its Optimistic Estimate is 12 days, and its Pessimistic Estimate is 28 days. What is our PERT Estimate?
18 Days
28 Days